Article: The Solange Argument as a Justification for Disobeying the Security Council in the Kadi Judgments

University of Oxford - Faculty of Law

November 7, 2013

KADI ON TRIAL: A MULTIFACETED ANALYSIS OF THE KADI JUDGMENT, pp. 121-134, Matej Avbelj, Filippo Fontanelli and Giuseppe Martinico, eds, Routledge, 2014 

Abstract:

The Kadi judgments of the courts of the EU have received enormous scholarly attention and have had significant practical impact. And reasonably so: they are landmark decisions, with numerous implications for several crucial issues, from the relationship between different legal orders to the primacy of Security Council decisions, from the required level of protection of fundamental human rights in the application of coer-cive measures against individuals to the competence of the EU, and so forth. This brief study focuses on one particular aspect of the Kadi decisions: their employment of the Solange argument as a justification for disobeying the Security Council by not implementing its binding decisions.

Number of Pages in PDF File: 12

Disponível em: <http://ssrn.com/abstract=2364764>. Acesso em 23 mar. 2014.

quinta-feira, 5 de dezembro de 2013

Blog post: German Federal Court of Justice refers question on lis-pendens-rule to ECJ

By Jonas Steinle, LL.M.


Jonas Steinle is a doctoral student at the chair of Prof. Dr. Matthias Weller, Mag.rer.publ. at the EBS University for Economics and Law in Wiesbaden and a scholarship holder at the Max Planck Institute for Intellectual Property and Competition Law in Munich.


On 18 September 2013 the German Federal Court of Justice (Bundesgerichtshof) referred the question for a preliminary ruling to the European Court of Justice (V ZB 163/12) as to whether the lis pendens-rule in Art. 27 para. 1 Brussels I Regulation does apply even if the court second seised has exclusive jurisdiction under Art. 22 of the Brussels I Regulation.


The facts:


The claimant seeks to enforce a land charge (Grundschuld) against the defendant’s real estate, which is located in Hamburg. He therefore brought an action in the regional court (Landgericht) of Hamburg. However, before this claim in Hamburg was launched, the defendant had already brought proceedings against the claimant in a court in Milan, seeking a negative declaratory relief that the land charge is invalid and that it therefore must not be enforced. As a result of this, two proceedings were pending simultaneously in Hamburg and in Milan.

The landlord and defendant in the Hamburg-based proceedings accordingly argued that the court in Hamburg must stay its proceedings according to Art. 27 para. 1 Brussels I Regulation until the court in Milan (which had been seised first) has ruled on its own jurisdiction. This application for suspension was rejected in all instances and finally was referred for final appeal (Rechtsbeschwerde) to the Federal Court of Justice.

The Federal Court of Justice takes the view that the regional court in Hamburg has exclusive jurisdiction under Art. 22 Brussels I Regulation to hear the case. However, as the regional court in Hamburg had been seised second, the Federal Court had doubts as to whether the regional court in Hamburg must stay its proceedings under Art. 27 para. 1 Brussels I Regulation even if it has exclusive jurisdiction under Art. 22 Brussels I Regulation.


Comments:


The manoeuvre which was performed by the defendant in this case is not new at all. The defendant launched what is called in international procedural law an ‘Italian torpedo’. However, the circumstances in which this torpedo was used are new and therefore have set a precedent.

The ‘Italian torpedo’ is a litigation tactic whereby the presumptive defendant of a claim anticipates the proceedings against him by bringing an action against the presumptive claimant on his part. Such claim usually consists of an application for a negative declaratory relief in a jurisdiction other than the one where the presumptive defendant is going to be sued. The objective in doing so is simply to delay the proceedings in the venue where the proceedings in the end will take place, since the court at that place which has been seised second must stay its proceedings according to Art. 27 para. 1 Brussels I Regulation until the court first seised has ruled on its jurisdiction. Usually, the courts in the jurisdiction where the Torpedo-claim is brought are known for being somewhat slow on the draw.

In the case at hand, there was hardly any connection to the courts of Italy. The enforcement of the land charge is a purely domestic claim under German law and the reason why the negative declaratory relief was sought in the courts of Italy in particular seems more like a flimsy excuse than a real substantiation of that claim. Accordingly, the appeal court (Beschwerdegericht) in Hamburg rejected to stay the proceedings because it alleged that the defendant in the Hamburg-based proceedings hat brought a vexatious claim in the courts of Milan, solely to delay the proceedings in Hamburg. The situation at hand can therefore very well be classified as an example of an ‘Italian torpedo’-claim.

In the past, the tactic of the ‘Italian torpedo’ often was used to thwart a jurisdiction agreement according to Art. 23 Brussels I Regulation. This was due to the Gasser case (C-116/02) in which the ECJ had ruled that even where the court second seised had exclusive jurisdiction according to a jurisdiction agreement, it must nevertheless stay the proceedings until the court first seised has decided on its jurisdiction. This ruling had opened up a debate about the lis-pendens-rule which finally induced the European legislator to introduce an exception to the lis-pendens-rule for jurisdiction agreements under Art. 31 para. 2 of the revised version of the Brussels I Regulation (Regulation (EU) No 1215/2012) which for the most part comes into force on 10 January 2015. The revision of the Brussels I Regulation will finally bring an end to the ‘Italian torpedo’ in connection with jurisdiction agreements.

The case at hand shows however, that the story of the ‘Italian-torpedo’ is not yet finished. Although this case is based on the same tactical considerations, the context is a slightly different one. It addresses an issue that had been left open by the ECJ in previous cases (C-351/89 – Overseas Union Insurance, para. 20 et seqq.; C-116/02 – Gasser, para. 44 et seqq.) and which has been subject to a controversial debate in legal literature (e.g. Weller in Hess/Pfeiffer/Schlosser, The Brussels I-Regulation (EC) No 44/2001, para. 403; see also the sources in para. 18 of the reference of the Federal Court of Justice).

It is conceivable that the ECJ will give precedence to the lis-pendens-rule yet another time and adopt the formal approach that it has been taking since the Gasser-case. The wording of Art. 27 para. 1 Brussels I Regulation does not provide for an exception in cases where the court second seised has exclusive jurisdiction under Art. 22 Brussel I Regulation.

The key consideration that justifies the very formal approach towards situations of lis pendens by the Brussels I Regulation is to avoid the risk of irreconcilable judgments in the European judicial area. Since decisions from other Member States are recognized and enforced on a regular basis under the Brussels I Regulation, the situation of irreconcilable judgments must by any means be prevented by hindering parallel proceedings from the scratch.

However, in the case at hand there appears to be one crucial difference to this argument and that is Art. 35 para. 1 Brussels I Regulation. According to Art. 35 para. 1 Brussels I Regulation a decision must not be recognised if it conflicts with Art. 22 Brussels I Regulation which is exactly the case in the proceedings at hand. If the ECJ is going to give precedence yet another time to the lis-pendens-rule, the Court cannot rely anymore on its argument that the lis-pendens-rule must prevail for the sake of hindering the issuance and recognition of conflicting decisions.

In fact, for the situation in the present case, the court in Milan is obliged to decline jurisdiction according to Art. 25 Brussels I Regulation if the Federal Court of Justice is right in holding that its requirements are fulfilled and the court in Hamburg therefore is competent to hear the case under Art. 22 Brussels I Regulation. One can however see in the case at hand that courts sometimes do not immediately use the tool provided in Art. 25 Brussels I Regulation (also the court of first instance in Milan did not use it) and that one possibly can litigate on whether the requirements of Art. 25 Brussels I Regulation are fulfilled. This does not make things easier for the present case and it is to be awaited how the European Court of Justice will decide on the issue. Eventually a decision can be expected in the near future since the higher regional court (Oberlandesgericht) München had already referred exactly the same question to the ECJ already in February 2012 (OLG München, 16 February 2012 – 21 W 1098/11).

sexta-feira, 29 de novembro de 2013

Blog post: ECJ Defines Concept of International Character of Consumer Contracts

by GILLES CUNIBERTI on NOVEMBER 18, 2013



On 14 November 2013, the Court of Justice of the European Union delivered its judgment in  Armin Maletic and Marianne Maletic v lastminute.com GmbH and TUI Österreich GmbH.

The issue for the Court was whether the Brussels I Regulation applied to a consumer contract concluded with a professional based in the same jurisdiction as the consumer.

On 30 December 2011, two Austrian consumers, the Maletics, booked and paid for themselves, as private individuals, a package holiday to Egypt on the website of lastminute.com for EUR 1 858 from 10 to 24 January 2012. On its website, lastminute.com, a company whose registered office is in Munich (Germany), stated that it acted as the travel agent and that the trip would be operated by TUI, which has its registered office in Vienna (Austria).

The booking concerned the Jaz Makadi Golf & Spa hotel in Hurghada (Egypt). That booking was confirmed by lastminute.com, which passed it on to TUI. Subsequently, the Maletics received a ‘confirmation/invoice’ of 5 January 2012 from TUI which, while it confirmed the information concerning the trip booked with lastminute.com, mentioned the name of another hotel, the Jaz Makadi Star Resort Spa in Hurghada. It was only on their arrival in Hurghada that the applicants in the main proceedings noticed the mistake concerning the hotel and paid a surcharge of EUR 1 036 to be able to stay in the hotel initially booked on lastminute.com’s website.

On 13 April 2012, in order to recover the surcharge paid and to be compensated for the inconvenience which affected their holiday, the applicants in the main proceedings brought an action before an Austrian Court seeking payment from lastminute.com and TUI, jointly and severally of the sum of EUR 1 201.38 together with interest and costs.

The Austrian court retained jurisdiction over Lastminute on the ground of Article 15 of the Brussels Regulation, but declined it with respect to the Austrian party, ruling that the Regulation did not apply to a domestic dispute, and that another Austrian court had jurisdiction pursuant to Austrian civil procedure.

The CJEU held that the dispute was international in character.

28 If, as stated in paragraph 26 of this judgment, the international character of the legal relationship at issue need not necessarily derive from the involvement, either because of the subject-matter of the proceedings or the respective domiciles of the parties, of a number of Contracting States, it must be held, as the Commission and the Portuguese Government have argued, that Regulation No 44/2001 is applicable a fortiori in the circumstances of the case at issue in the main proceedings, since the international element is present not only as regards lastminute.com, which is not disputed, but also as regards TUI.

29 Even assuming that a single transaction, such as the one which led the Maletics to book and pay for their package holiday on lastminute.com’s website, may be divided into two separate contractual relationships, first, with the online travel agency lastminute.com and, second, with the travel operator TUI, the second contractual relationship cannot be classified as ‘purely’ domestic since it was inseparably linked to the first contractual relationship which was made through the travel agency situated in another Member State.

30 Furthermore, account must be taken of the objectives set out in recitals 13 and 15 in the preamble to Regulation No 44/2001 concerning the protection of the consumer as ‘the weaker party’ to the contract and the aim to ‘minimise the possibility of concurrent proceedings … to ensure that irreconcilable judgments will not be given in two Member States’.

31 Those objectives preclude a solution which allows the Maletics to pursue parallel proceedings in Bludenz and Vienna, by way of connected actions against two operators involved in the booking and the arrangements for the package holiday at issue in the main proceedings.

Ruling:

The concept of ‘other party to the contract’ laid down in Article 16(1) of Council Regulation (EC) No 44/2001 of 22 December 2000 on jurisdiction and the recognition and enforcement of judgments in civil and commercial matters must be interpreted as meaning, in circumstances such as those at issue in the main proceedings, that it also covers the contracting partner of the operator with which the consumer concluded that contract and which has its registered office in the Member State in which the consumer is domiciled.